Side 24 av 25
Analyse av utviklingen innen transformatorer, transformatorstasjoner og nett, skrevet for dem som drifter anleggene. Hver artikkel er vår egen vurdering av en utvikling – vi lenker til kilden i stedet for å gjengi den.
277–288 av 298
NamPower sets 70% renewable energy target by 2030
NamPower plans major solar, wind and battery storage projects to reach 70% renewable generation by 2030, driving transformer and substation upgrades.
Omtalt av AllAfrica

TEİAŞ Reports Remaining Distribution-Level Unlicensed Capacity
TEİAŞ confirms that remaining unlicensed solar and wind distribution capacity across transformer substations in Türkiye has dropped to 624 MW.
Omtalt av Enerji Günlüğü

Jordan Desalination Project Integrates 281 MW Solar Plant
Jordan’s 6 billion dollar water scheme uses a 281 MW solar plant and grid supply for a 438 km pipeline, supplying 300 million cubic metres with 27 percent solar
Omtalt av Yeşil Haber

Eskom reaches 500 days without load shedding as generation availability hits 68.11%
South Africa marks over 500 days without load shedding with EAF reaching 68.11%, offering utilities a window for critical substation maintenance.
Omtalt av Eskom
North Macedonia begins €46 million hydropower plant modernisation phase
North Macedonia starts a €46 million upgrade across six hydropower plants, adding 13.5 MW in capacity and 50 GWh of annual energy generation.
Omtalt av SEE Energy News

National Grid Allocates £600M Substation Civils Framework Across 31 Suppliers
National Grid Electricity Distribution selects 31 civil engineering partners for a £600M framework to prepare substation compounds for network growth.
Omtalt av New Civil Engineer

Türkiye Unlicensed Renewable Grid Capacity Drops Near Zero
TEİAŞ transmission capacity map shows available headroom for unlicensed solar and wind power dropped from 1.500 MW down to 38.3 MW in Türkiye.
Omtalt av Yeşil Haber

South Africa advances independent transmission programme to unlock grid capacity
South Africa reaffirms its independent transmission programme, launching the next procurement phase to fund new substations and transmission corridors.
Omtalt av Infrastructure News

Sarajevo 12 Substation Online to Reinforce Bosnia 110 kV Grid
Elektroprijenos BiH has commissioned the Sarajevo 12 110 kV substation, deploying 40 MVA transformers to relieve Sarajevo 7 and Sarajevo 13 nodes.
Omtalt av Transformer Technology

NESO Seeks 1-Month Extension From Ofgem for Gate 2 Phase 1 Grid Offers
NESO has requested a 1-month delay from regulator Ofgem to process complex transmission connection offers under Phase 1 of its Gate 2 reform.
Omtalt av Solar Power Portal

Zambia approves 350 MW wind plant and 330 kV grid link
Environmental approval for Zambia's 350 MW wind project with 42 turbines requires a 330 kV substation and line expansion to ensure power evacuation.
Omtalt av Lusaka Times

Hybrid renewable expansion in Bulgaria underscores grid integration demands
Renalfa IPP and Eurowind Energy inaugurate the enlarged Tenevo hybrid renewable complex in Bulgaria, presenting collector substation challenges.
Omtalt av Balkan Green Energy News
Start med en tilstandsvurdering
Fortell oss om anleggene, stedet og situasjonen. Er tilstanden i transformatorparken ukjent, er en tilstandsvurdering den minst forpliktende måten å finne ut hva dere faktisk har på – og den legger grunnlaget for det som kommer etterpå.