Bucharest West CHP plant reconnects to Romanian grid after switchgear repairs
ELCEN completes six months of restoration at Bucharest West CHP, energising 6 kV and 0.4 kV auxiliary switchgear following electrical fire damage.

Switchgear restoration and thermal plant recovery
The return of the Bucharest West combined heat and power facility to Romania's power system on 15 November 2026 marks the end of a 6-month forced outage. The shutdown followed compounding electrical failures, beginning with initial equipment damage and a major fire that compromised internal plant distribution networks. To restore generating capability, site engineering teams focused on rebuilding the auxiliary power infrastructure, specifically returning the 6 kV and 0.4 kV busbars and switchgear to operational status.
Auxiliary switchgear and medium-voltage distribution systems form the operational backbone of thermal power plants, feeding cooling pumps, fuel handling systems, excitation equipment and control electronics. When fires occur within switchboards or cable galleries, secondary damage from smoke, soot deposition and fire suppression mediums often forces a complete stripping and replacement of switchboards, protection relays and low-voltage control cabling. A 6-month lead time for complete decontamination, switchgear procurement, installation and testing highlights the severe supply-chain and operational friction associated with indoor substation and switchgear fires.
For plant engineers and grid operators, this event illustrates the vulnerability of power station auxiliary networks. While primary step-up transformers receive extensive monitoring, auxiliary 6 kV and 0.4 kV switchgear often operate with basic overcurrent protection and periodic insulation testing. A busbar fault or arc flash incident in auxiliary equipment can result in immediate plant tripping, thermal shock to steam turbines and extended loss of commercial availability.
What this means for asset owners in the Balkans and the Black Sea region: Thermal and combined-cycle plant managers across Romania and neighbouring grid areas must re-evaluate fire suppression and arc-flash mitigation across medium-voltage switchgear installations. A 6-month unbudgeted outage arising from 6 kV or 0.4 kV auxiliary switchboard damage underlines the necessity of continuous partial discharge monitoring, regular thermal imaging and upgraded busbar arc protection to reduce catastrophic fire risks and secure grid availability.