Skip to content
/programmes/substation-services

Substation rehabilitation, testing and maintenance

Primary and secondary equipment across the substation, not only the transformer.

Looking up at high-voltage disconnectors and tall ribbed insulator columns on lattice steel gantries, with a technician working from a mobile elevating work platform against a blue sky
Working at height on disconnector connections from a mobile elevating work platform.
01Who it is for

Who substation rehabilitation and maintenance is for

Substation rehabilitation and maintenance covers the equipment around the transformer: circuit breakers and disconnectors, current and voltage transformers, protection relays, earthing, cables, and the secondary systems that supply and control them. Each item is tested to a published method and serviced, and where the survey shows it is needed, the work is brought together as a rehabilitation package for the substation.

  • TSOs, DSOs and utilities with ageing substations

    Reliability targets to meet with ageing primary and secondary equipment, and each intervention to be justified with test evidence, item by item.

  • Network rehabilitation programmes

    Substation rehabilitation funded through a regulated investment plan or a development-bank programme, scoped per substation and documented item by item.

  • Industrial operators with their own MV networks

    Plants and industrial zones that operate their own medium-voltage substations, such as the organised industrial zones in Türkiye.

  • Renewable and storage collector substations

    Collector substations at solar, wind and battery storage sites, frequently remote, with switchgear and protection that the plant's availability depends on.

02What the programme includes

Primary and secondary substation equipment the programme covers

The work on each item is testing, adjustment, cleaning, parts replacement and recommissioning, as the survey finds it needed.

  1. HV switchgear and circuit breakers

    Service and timing of circuit breakers: operating times and main-circuit resistance measured to IEC 62271-100, and the mechanism adjusted where the results call for it.

  2. Disconnectors and earthing switches

    Main-circuit resistance measured to IEC 62271-102, with mechanical adjustment and parts replacement where the results or the inspection call for it.

  3. Current and voltage transformers

    Current transformers tested to IEC 61869-2 and capacitive voltage transformers to IEC 61869-5: accuracy, capacitance and dissipation factor, and for current transformers the knee point and the secondary winding resistance.

  4. Busbars, arresters, insulators and panels

    Busbars, surge arresters, insulators, capacitors, busducts and MV switchgear panels: mechanical adjustment, cleaning and parts replacement, and silicone (RTV) coating of insulators.

  5. Protection relays, tested by secondary injection

    Protection relays tested by secondary injection to IEC 60255-1, and configured where the scheme calls for it.

  6. Secondary systems

    AC and DC supplies, battery banks, LV switchgear, control and SCADA systems, compensation, UPS and communications. Valve-regulated station batteries are tested for capacity to IEC 60896-21.

  7. Earthing and ground-grid testing

    Earth electrode and ground-grid resistance measured to IEEE 81, and soil resistivity where it is needed.

  8. MV cable testing

    Very-low-frequency (VLF) AC withstand testing to IEEE 400.2 after installation or repair, and the test after installation that IEC 60502-2 sets for extruded cables.

  9. Thermographic surveys

    Thermal imaging of energised plant under load to ISO 18434-1, which finds hot connections and contacts without an outage.

  10. Substation rehabilitation packages

    Scoped per substation from the survey: retrofit of breakers and relays in LV and MV switchboards, redrawing of secondary schemes where drawings are missing or out of date, and recommissioning.

03How it runs

How substation maintenance runs around your outage windows

Phases, in order, inside the eight stages every programme follows. Work that needs a bay or a circuit switched out is planned into the outage windows your network allows.

  1. Survey

    What is installed, its condition, its drawings and the outages available, established on site.

  2. Test and inspect

    Each item tested to its method and inspected, and energised plant surveyed thermally under load.

  3. Service, adjust and replace

    Mechanisms adjusted, contacts and parts replaced, insulators cleaned and relays configured, as the findings set.

  4. Re-test

    The same tests repeated after the work, so that each item returns to service with a result.

  5. Records

    Results filed per item, each with its method, ready for the next outage plan.

What you provide

  • The assets and the site

    The organisation, the site, the number of transformers with their rating and voltage ranges, the situation and your timeline: what the enquiry form asks for.

  • Existing records

    DGA results, oil analysis and test reports, sent as a reply to our acknowledgement. A result means more when it is read against the same unit's history.

  • Outage windows

    When each unit can be switched off, whether a regulated outage plan or a load-shedding rota sets it. Tests and work that need a de-energised unit are planned into those windows.

  • Access to the site

    Access, ground conditions, crane availability and supply, confirmed at the site survey before a price is fixed.

04What you receive

What you receive for each substation

  • Test records per item

    Operating times, contact resistance, relay tests, earth resistance and thermal images, each with the method it was carried out to.

  • A scoped rehabilitation package

    Where the survey shows it is needed: what to retrofit, which schemes to redraw and what to recommission, substation by substation.

  • Recommissioned equipment

    Items serviced, tested again and returned to service, with the result that shows it.

05The technical basis

Circuit breaker, relay, earthing and cable test standards

Each test follows a published method, and the method is recorded with the result. Citing a method says how the work is done and what it is measured against.

Standards the work and the report follow
StandardWhat it governs here
IEC 62271-100Circuit-breaker operating times and main-circuit resistance
IEC 62271-102Main-circuit resistance of disconnectors and earthing switches
IEC 61869-2Current transformer tests
IEC 61869-5Capacitive voltage transformer tests
IEC 60255-1Protection relay tests, including secondary injection
IEC 60896-21Capacity of valve-regulated station batteries
IEEE 81Earth resistance and soil resistivity
IEEE 400.2VLF AC withstand testing of cables
IEC 60502-2Voltage test on extruded cables after installation
ISO 18434-1Thermography of energised plant

The detail on the capabilities page

06Questions

Substation rehabilitation and maintenance: common questions

What does the programme cover beyond the transformer?

Primary equipment — circuit breakers, disconnectors, current and voltage transformers, busbars, surge arresters, insulators, capacitors, busducts, cables and MV switchgear panels — and secondary equipment: protection and control relays, AC and DC supplies, battery banks, LV switchgear, control and SCADA systems, compensation, UPS and communications. The work is testing, adjustment, cleaning, parts replacement and commissioning.

How are circuit breakers tested?

The opening and closing times are measured, and so is the resistance of the main circuit across the contacts, to the methods in IEC 62271-100. The results are compared with the manufacturer's values and with the breaker's earlier results, so that a slowing mechanism or worn contacts are found before the breaker is asked to clear a fault.

What is secondary injection testing?

It tests a protection relay by feeding currents and voltages from a test set into the relay's inputs to simulate fault conditions, and recording whether and when the relay operates. It proves the settings and the relay's response without a fault on the primary system. Relay tests are carried out to IEC 60255-1.

How is a substation earthing system tested?

The resistance of the earth electrode or grid is measured, together with soil resistivity where a design or a rehabilitation needs it, to the methods in IEEE 81. The result is compared with the design value and with earlier measurements, because corrosion and changing ground conditions move it over the years.

Why carry out thermographic surveys?

A thermal image taken under load finds connections, bushing terminals and contacts that are running hot, which marks where energy is being lost and where a fault may be developing. The plant stays energised, so the survey needs no outage, and it tells the next outage plan where to look first. Surveys follow ISO 18434-1.

How are medium-voltage cables tested after installation or repair?

After installation or repair, cable insulation is proved with a very-low-frequency AC withstand test to IEEE 400.2. For extruded cables, IEC 60502-2 sets the test after installation. The test voltage and duration follow the cable's rating and the standard, and the results are recorded with the method for the owner's cable records.

Scope this programme for your site

Tell us the assets, the site and the situation. The enquiry form opens with this programme already selected.