ESB doubles Julianstown 38 kV substation transformer capacity to 20 MVA

ESB Networks replaces 5 MVA transformers with 10 MVA units at Julianstown 38 kV substation in Ireland, expanding grid capacity to 20 MVA.

Imagem: Transformer Technology

Distribution network operator ESB Networks has upgraded its Julianstown substation operating at 38 kV in County Meath. The project doubled the site capacity from 10 MVA to 20 MVA by removing legacy 5 MVA units and installing two 10 MVA transformers. This added 10 MVA of net capacity to support growing demand on the regional distribution network.

Replacing aged 5 MVA units with higher-capacity 10 MVA transformers within existing substation boundaries is a crucial strategy for distribution operators facing rising load growth. Operating 38 kV infrastructure under tighter thermal margins heightens the importance of transformer cooling and load management. Doubling capacity from 10 MVA to 20 MVA allows utilities to integrate expanding residential, commercial, and electrification loads without major civil expansion or acquiring new land plots.

For engineering teams, swapping legacy 5 MVA units with modern 10 MVA transformers demands careful evaluation of existing foundations, oil containment systems, and protection schemes. Higher rated 10 MVA units alter fault current levels on the 38 kV busbars and secondary feeders, necessitating adjusted relay settings and busbar withstand verifications. Additionally, managing thermal performance under seasonal peak loads ensures long-term asset health across extended service lives.

What this means for asset owners in the UK and Ireland: Distribution utilities and plant managers in Ireland upgrading legacy 38 kV substations must review physical clearances, foundation load ratings, and oil containment bund capacities when replacing 5 MVA transformers with 10 MVA units. Upgrading to a 20 MVA total capacity requires re-evaluating short-circuit fault levels and switchgear ratings to maintain system reliability during peak operational demand.